CREAM-VI Major Milestones

Sep. 28 – Oct. 5 2009: CERN Beam Calibration.
Jan. 26 – 29: ISS (Instrument Support Structure) build-up.
Mar. 11: Delivery of CREAM-V air-lift high priority recovery items.
Mar. 22 – 29: Chercam visual inspection, refurbishment and test.
Apr. 12: Delivery of 2 GSE crates and recovery tool box.
Apr. 13: Delivery of CREAM-V sea container.
Apr. 1 – 20: SCD test and refurbishment.
Apr. 26: Chercam mechanical integration to ISS.
Apr. 27 – 28: SCD mounting and alignment test.
Apr. 30 – May 3: Re-stacking of the ISS.
May 4 – 13: CSBF connection test.
May 28 – Jun. 16: SCD cable replacement, CPT, alignment, and closing.
Jun. 17 – Jul. 1:  Integration and long term burn-in.
Jul. 6:  Shipping instrument to CSBF.
Jul, 8 – 28:  Integrate instrument with SIP & balloon-craft buildup at CSBF.
Jul. 29 – Aug. 2: Hang-test at CSBF.
Aug. 3 – 6: Packing for shipment to the Ice.
Aug. 16: MRR (Mission Readiness Review).
Aug. 16&24: GSE sea containers shipping to the Ft. Hueneme from CSBF.
Oct. 15: Instrument container arrived at McMurdo station ( from D. Sullivan).
Nov. 5: Arrival of launch crews at McMurdo station. (Local time).