BEAM TEST PLANNING GUIDE
|
-6o days |
Reserve CERN hostel rooms |
|
-30 days ~ -14 days |
Make plans for a trip
to Geneva; |
|
-10 days |
Shipper to pick up the crates |
|
-5 days |
Crew departure; Crates arrival at CERN |
|
-4 days |
Crew to user’s office for registration, radiation badges; unpack crates, mount the instrument on the rotation fixture, test etc. |
|
-1 day |
Reserve the crane; make a shift schedule |
|
0 day |
Stage in to the beam area Set up the beam, trigger, tracker, and the instrument |
|
Beam Time |
Take the data; repair as needed; Reserve the crane for last day; Arrange the shipper to pick up crates |
|
End beam time |
Crane out |
|
+ 5 hrs |
Packed & Move crates from CERNII to CERN I; Shipper to pick up the crates |
|
+ 1 (or 2) day |
Crew Return |