2005 Major Milestones
09/08 - 09/11 Final assembly of Calorimeter 09/12 - 09/15 Cookie alignment 09/15 - 09/18 SCD in stallation, system troubleshoot, test 09/19 Pack and ship to CERN 09/20 - 09/26 Prepare BT (beam tracker) 09/26 Ship BT and supplemental supplies to CERN 09/27 UMD crew arrive at CERN 10/02 - 10/11 Beam Test at CERN October - November Final instrument structural analysis and thermal design 10/01 - 12/31 Fabricate, new ISS Components, certify old ISS components