Cosmic Ray Energetics And Mass (CREAM)

  • Increase font size
  • Default font size
  • Decrease font size
Home CREAM Data Flight 2007 Data

CREAM 2007 Flight Data

Print PDF
SCIENCE TEST DATA
SCIENCE FLIGHT DATA
INSTRUMENT CONFIGURATION
Last Updated on Sunday, 14 December 2008 13:10  

CREAM III Investigators and Collaborators

Principal Investigator


Collaborators

Official CREAM Logo

CREAM Logo

CREAM III Flight Trajectory

Click the map below to see the CREAM III flight trajectory.

CREAM III flight trajectory

2007 Major Milestones

01/04 TCD mechanically integrated
01/25 CherCam+CD mechanical fit-check
04/26 CherCam T-Vac test completed
04/30 Instrument mechanical integration complete
05/01-07/08 Electronic & data integration & testing
07/09 Instrument delivered to WFF (truck incident)
07/09-09/06 CREAM payload integration & testing
09/07 Mission Readiness Review
09/16 CDM & Ground support equipment shipped out of WFF
09/28 SFC1 replaced with SFC3
10/05 Last access to instrument
10/15 Instrument & shipped out of WFF
11/11 Science & WFF crew arrive McMurdo
11/12 GSE delivered to payload building
11/13 Instrument delivered to payload building
11/15 Instrument CPT completed
11/17 Joint LPT completed
11/19 End-to-end data flow test
11/27 Batteries delivered to payload building
12/03 Ready for hang-test
12/04 Hang test
12/04 Flight Ready
12/19 Launch