Cosmic Ray Energetics And Mass (CREAM)

  • Increase font size
  • Default font size
  • Decrease font size
Home CREAM Flights CREAM IV
CREAM Flight 2008

CREAM-IV at McMurdo, Nov. 14th 2008

Print PDF
Dear,

Here is a summary of CREAM-IV flight preparation status on the 14th of November at McMurdo.
  • For most of day, TCD/CD data were taken with different threshold values for the calibration of the threshold values.
Last Updated on Friday, 21 November 2008 22:07 Read more...
 

CREAM-IV at McMurdo, Nov. 13th 2008

Print PDF
Dear,

Here is a summary of CREAM-IV flight preparation status on the 13th of November at McMurdo.
  • The TCD dead time debugging continued with threshold value increase in the ZHi trigger. Then the even number mismatch error reduced dramatically and the live time increased to about 90% in flight mode. To understand the correct ZHi threshold values for the flight, Tyler has asked Nick/Isaac. This is done with the default cdaq code.
Last Updated on Friday, 21 November 2008 22:07 Read more...
 

CREAM-IV at McMurdo, Nov. 12th 2008

Print PDF
Dear,

Here is a summary of CREAM-IV flight preparation status on the 12th of November at McMurdo.

  • TCD problem with the PMT#4/5 HV resolved by reconnecting the 12 V power line to the HV PS which was cut during the HSK circuit modification.
  • After that the hkconv4.dat file modified to have correct value in TCDPwr12. The new hkconv4.dat file will be updated into the relevant computers.
Last Updated on Friday, 21 November 2008 22:07 Read more...
 

CREAM-IV at McMurdo, Nov. 11th 2008

Print PDF
Dear,

Here is a summary of CREAM-IV flight preparation status on the 11th of November at McMurdo.
  • The CREAM instrument is now on its legs after removing the moving table that supported it.
  • Solar panels preparation work started in the afternoon when the wind becomes lighter. But still it was a rather windy day.
Last Updated on Friday, 21 November 2008 22:07 Read more...
 

CREAM-IV at McMurdo, Nov. 10th 2008

Print PDF
Dear,

Here is a summary of CREAM-IV
Last Updated on Friday, 21 November 2008 22:08 Read more...
 


Page 8 of 12

Time Zones

Official CREAM Logo

CREAM Logo

CREAM IV Flight Trajectory

Click the map below to see the CREAM IV flight trajectory.

CREAM IV flight trajectory

2008 Major Milestones

Jan:  Delivery & mechanical fit-check of upper structure
Mar 12:  Delivery of recovered CREAM-III detector systems.
Mar-May:  Refurbishment of detector systems.
Apr 14-18:  Assembly of the upper structure.
May 5-9:  Integration of TCD.
May 12-16:  Integration of Chercam.
Jun. 3:  Integration of the SCD.
Jun. 3:  Mechanical integration of the CD.
May-Jun:  Integration and long term burn-in.
Jul 7:  Shipping instrument to CSBF.
Jul 9-31:  Integrate instrument with CDM & balloon-craft buildup at CSBF.
Aug. 1-5: Hang-test and long term burn-in at CSBF.
Aug. 20: Mission Readiness Review .
Aug. 18: GSE sea containers ship to the ICE from CSBF.
Aug. 28: Instrument sea container ship to the ICE from CSBF.
Sep. 8: Instrument sea container arrive at Christchurch, NZ.
Oct. 23: Mission Operations Review.
Nov. 7 (NZT) : First 5 launch crews arrive at McMurdo
Nov. 9-30 (NZT): Integrate instrument with CDM & balloon-craft building at Willie Field
Dec. 1 (NZT): Hang-test at Willie Field, CREAM-IV Flight ready
Dec. 3 (NZT): WFF Flight Readiness Review (FRR)