The SOC has started the shutdown procedure of the CREAM-IV science instruments from the request of the WFF ESC in order to have the CREAM-IV flight to be terminated at 4:30 AM (EST). We are now waiting for the calorimeter HV ramping down.

Best, MooHyun.
 

Time Zones

Official CREAM Logo

CREAM Logo

CREAM IV Flight Trajectory

Click the map below to see the CREAM IV flight trajectory.

CREAM IV flight trajectory

2008 Major Milestones

Jan:  Delivery & mechanical fit-check of upper structure
Mar 12:  Delivery of recovered CREAM-III detector systems.
Mar-May:  Refurbishment of detector systems.
Apr 14-18:  Assembly of the upper structure.
May 5-9:  Integration of TCD.
May 12-16:  Integration of Chercam.
Jun. 3:  Integration of the SCD.
Jun. 3:  Mechanical integration of the CD.
May-Jun:  Integration and long term burn-in.
Jul 7:  Shipping instrument to CSBF.
Jul 9-31:  Integrate instrument with CDM & balloon-craft buildup at CSBF.
Aug. 1-5: Hang-test and long term burn-in at CSBF.
Aug. 20: Mission Readiness Review .
Aug. 18: GSE sea containers ship to the ICE from CSBF.
Aug. 28: Instrument sea container ship to the ICE from CSBF.
Sep. 8: Instrument sea container arrive at Christchurch, NZ.
Oct. 23: Mission Operations Review.
Nov. 7 (NZT) : First 5 launch crews arrive at McMurdo
Nov. 9-30 (NZT): Integrate instrument with CDM & balloon-craft building at Willie Field
Dec. 1 (NZT): Hang-test at Willie Field, CREAM-IV Flight ready
Dec. 3 (NZT): WFF Flight Readiness Review (FRR)