Cosmic Ray Energetics And Mass (CREAM)

  • Increase font size
  • Default font size
  • Decrease font size
Home CREAM Flights Flight 2008 (CREAM IV) Re: CREAM-IV flight termination at 4:30 AM

Re: CREAM-IV flight termination at 4:30 AM

Print PDF
Dear,

Now the CREAM-IV instrument is off including SFC. It was January 7th 3:34 AM (EST) when the instrument HV/Bias shutdown had started.

And the CDM has started shutting down around 4:05 AM (EST).

Thanks. MooHyun.
 

Official CREAM Logo

CREAM Logo

Current Status

Getting ready for flight.
Flight Launch, Dec 18, 2008
04:54:45 PM EST
McMurdo Station, Antarctica

CREAM IV Flight Trajectory

Click the map below to see the CREAM IV flight trajectory.

CREAM IV Flight Trajectory

2008 Major Milestones

Jan:  Delivery & mechanical fit-check of upper structure
Mar 12:  Delivery of recovered CREAM-III detector systems.
Mar-May:  Refurbishment of detector systems.
Apr 14-18:  Assembly of the upper structure.
May 5-9:  Integration of TCD.
May 12-16:  Integration of Chercam.
Jun. 3:  Integration of the SCD.
Jun. 3:  Mechanical integration of the CD.
May-Jun:  Integration and long term burn-in.
Jul 7:  Shipping instrument to CSBF.
Jul 9-31:  Integrate instrument with CDM & balloon-craft buildup at CSBF.
Aug. 1-5: Hang-test and long term burn-in at CSBF.
Aug. 20: Mission Readiness Review .
Aug. 18: GSE sea containers ship to the ICE from CSBF.
Aug. 28: Instrument sea container ship to the ICE from CSBF.
Sep. 8: Instrument sea container arrive at Christchurch, NZ.
Oct. 23: Mission Operations Review.
Nov. 7 (NZT) : First 5 launch crews arrive at McMurdo
Nov. 9-30 (NZT): Integrate instrument with CDM & balloon-craft building at Willie Field
Dec. 1 (NZT): Hang-test at Willie Field, CREAM-IV Flight ready
Dec. 3 (NZT): WFF Flight Readiness Review (FRR)