System Integration Review, April 11, 2014

System Integration Review
Wallops Flight Facility Building E-106, Room 217

Friday, April 11, 2014

10-10:15           Open Remarks – Keith Chamberlin

10:15 – 11:15  Program Introduction and Status – Linda Thompson

  • At-A-Glance
  • Mission/System-level Documentation
  • Payload Description
  • Responsibilities
  • Subsystem Qualification
  • Acceptance Data Package
  • Current Status: Supplier, Delivery Date, Testing and Waivers, Risk
  • Top-Level Schedule
  • Reserves Recovery  Options
  • NRL Status
  • KSC Status

11:15 – 12:00  Verification Matrices and Risks – Pete Patterson

  • JEM-EF ICD, JX-ESPC-101129
  • JAXA EF Payload C&DH ICD, SSP 57294
  • C&DH Interface, SSP-57000
  • STELLA Verification, SSP 52000
  • SpaceX ICD, 
  • CREAM Software ICD, Revision A, SSP 57319
  • Project Risks

12:00 – 1:00    Lunch

1:00 – 1:45      Integration and Test – Chris Rose

  • Personnel Support/Certification and Training
  • Facility Readiness at Wallops
  • Wallops Day-to-Day Activities
  • Wallops I&T Flow
  • NRL I&T Flow
  • Launch Site, KSC – SSPF
  • Launch Site, SpaceX - LC–40
  • Documentation Status
  • GSE Status

1:45 – 2:00    Closeout – Keith Chamberlin