CREAM-IV calibration, CERN 9/13/2007-9/25/2007
CREAM-III calibration,CERN 10/2/2006-10/10/2006
CREAM-II calibration, CERN 9/22/2004-9/29/2004
Heavy Ion Beam Test, CERN, October 2003
2003 Heavy ion beam test schedule
Calibration at CERN, July & September 2003:
Real Time Monitoring of the Beam Test 2003
Parasitic Run at H8 (2002):
Preparation Guide 2002
Protoflight Test at CERN (2001)
BEAM TEST PLANNING GUIDE
-6o days |
Reserve CERN hostel rooms |
-30 days ~ -14 days |
Make plans for a trip to Geneva; |
-10 days |
Shipper to pick up the crates |
-5 days |
Crew departure; Crates arrival at CERN |
-4 days |
Crew to user’s office for registration, radiation badges; unpack crates, mount the instrument on the rotation fixture, test etc.
|
-1 day |
Reserve the crane; make a shift schedule |
0 day |
Stage in to the beam area Set up the beam, trigger, tracker, and the instrument |
Beam Time |
Take the data; repair as needed; Reserve the crane for last day; Arrange the shipper to pick up crates |
End beam time |
Crane out |
+ 5 hrs |
Packed & Move crates from CERNII to CERN I; Shipper to pick up the crates |
+ 1 (or 2) day |
Crew Return |