Dear,

Here is a summary of CREAM-IV flight preparation status on the 16th of November at McMurdo..

  • The SFC2 problem was debugged in the whole afternoon and resolved by replacing the USB cable.
  • NSF head office had a visit to the LDB facility and also to our CREAM integration building.
  • Dave Stuchlik and Chris continue working on the CDM preparation.
  • Tomorrow, the CPT will continue. Plan to finish by the end of tomorrow. It looks tight due to an unexpected longer time spent on the SFC2 debugging. But will try out best.

Cheers, MooHyun.