Dear,

After submitting 6 notebook computers for scanning at the Crary lab IT tech support, we attended the NSF briefing at the Chalet at 10 AM. There were 4 science teams in the briefing. By the number, the LDB participants (CREAM, 5 / ANITA, 10) were the majority. Will have to get an environmental field brief on Monday from 8 AM. After taking all 6 notebook computers back from the IT support, we went to the Willie field for a work. In the integration building, we have finished the followings for today.

  • Arrange tables for GSE and users' spaces temporarily.
  • Unpack GSE crates and setup GSE.
  • Check cabling on the instrument to see if there are any damages during the shipment. The TCD is done by Tyler, Chercam by Antje, and Calorimeter and common electronics done by SangEun and myself.
  •  

Power on procedure and LPT up to the calorimeter has been completed. Everything was OK so far.

  • Next time, the remaining SCD/Chercam/TCD LPT will be continued.
  • Since the building UPS is not ready, the instrument and client PCs are turned off for a safety.

Cheers, MooHyun.