Dear colleagues,
Here is a summary of today's activities at CSBF.
- CPT of instrument started. This time, SangEun is the one who excuted all the command and recording.
- CPT of SFC1/2 finished. Some of procedures in the manual need to be corrected and will be done.
- CPT of most of common electronics boards done up to the number 7.n. before the testing of the prescaler.
- Housekeeping board 2ndary boot source did not work during the CPT. Prashant will work on this with Larry's help.
- Just during the muon run in flight mode starting, Prashant found the mxr problem disappeared. But as soon as I touched a cable, which I don't remember, the problem came back. It may mean that there is a bad connection in the box?
Here are things to do until next Tuesday when Dave comes here.
- CPT of instrument.
- TCD mxr debugging.
- S3 tuning.
- CD housekeeping conversion factor in the housekeeping table.
- CDAQ remaining works including reduced housekeeping. (Prashant)
- Power cables for CDM shipping on Monday. (Larry)
- etc...
Please let us know if you have any questions/comments/suggestions.
Cheers, MooHyun.
MooHyun, July 12, 2008