Before starting CPT, Ludo checked HSK box
and fixed some red color parameters
on the HSK monitor and made them to green ones
(on tSCD/CherCam).
We finished Instrument CPT in the afternoon,
and continued CAL CPT.
We will finish all CPTs by tomorrow.
Tomorrow afternoon, we will connect SIP to our SEI computer locally
so that we can send commands and get data through SIP.
We expect to finish Combined CPT by 11/10/Wed(NZT).
If everything goes well, we will try a connection test with SOC on 11/11/Thur (NZT).
Today, it was clear and warm in the morning, but in the field it was changed to strong wind in the afternoon.
KC